Re: New Burnham boiler cycling


[ Follow Ups ] [ Post Followup ] [ Boiler Room Residential and Home Forum #4 ] [ FAQ ]

Posted by HeatPro on November 30, 2008 at 09:58:20:

In Reply to: Re: New Burnham boiler cycling posted by rbeck on November 30, 2008 at 07:37:02:

{{{Manufactureres already deduct 33% for the piping. }}

It is already deducted in the IBR sq ft of steam rating on the nameplate; butt ...
it isn't part of the burner input rating, so when considering burner input, the extra over connected load has to be added to account for piping and pickup allowance.

IOW, when input only is known, you then have to do what IBR already did for you.